CHARLESTON AIR FORCE BASE, S.C. –
Base Theater complete interior and exterior renovation: Current contract completion date: June.
Military family housing demolition: MFH demolition continues in south housing and Lawson Drive. 237 houses under contract, 106 completed. Estimated completion date: September.
Military family housing construction phase 4: Water, sewer, gas line complete. Storm piping, electrical and roads progressing. All 13 retaining walls in Hunley Park have been completed. All 10 new units framed. Estimated completion date: March 2008.
Bowling alley interior and exterior renovation: Interior complete. Exterior 98 percent complete; estimated completion date: This month.
Operations group headquarters: Complete interior and exterior renovation. Demolition in progress. Estimated completion date: October 2007.
Fitness and Sports Center: 5,800 square foot addition with accompanying 8,065 square feet of interior renovations, to include upgrade of the female locker room. Estimated start date: TBD, proposal received and being evaluated. Estimated completion date: May 2008.