Joint Base Headquarters renovation, Building 1600: Second floor demolition complete, steel stud installation began Feb. 3.
Child Development Center: Approved land disturbance permit package. Finalizing groundbreaking ceremony preparations for Feb. 13 at 2 p.m.
Chapel addition and renovation: Slab for new addition in progress. Interior demolition has begun, rerouting McCombs Way jogging trail in vicinity of construction.
Repair Runway 03/21: Pre-construction kick-off meeting held Jan. 29. Contractor working on submittals and testing approval. Estimated construction start date April 9.