CHARLESTON AIR FORCE BASE, S.C. –
Current construction
Runway 03/21 Repair: Construction workshop to be completed Feb. 27. Runway closure scheduled to begin April 9 with a 60-day intersection closure beginning May 11.
Chapel addition and renovation: Exterior brick work on the addition had begun. Sixteen percent of the construction is completed and is six percent ahead of schedule.
Fitness Center : Structural steel and bar joists are being placed, with removal of interior wall covering underway.
Utility outages:
-None scheduled.
Traffic impacts:
-None scheduled.